I. Construction project name and summary
Project Name: Annual production of 600,000 cubic meters of flame retardant particleboard project
Construction unit: Shandong Heze Maosheng Wood Industry Co., Ltd.
Project Location: Zhuangzhai Town Industrial Park, Cao County, Heze City, Shandong Province
Nature of the project: new construction
Construction Content: Construction content: 22-storey workshop, 16-storey workshop , flat-press line workshop, warehouse 1#, warehouse 2# , office building, staff quarters, restaurants, etc. Site area: about 310 acres. The construction period of the project is initially set at 12 months.
The total investment of the project is estimated to be 698 million yuan, of which the engineering cost is 547.80 million yuan, the other construction cost is 4.2 million yuan , the project preparation fee is 26 million yuan, and the initial working capital is 120 million yuan.
2. Name and contact information of the construction unit of the construction project
Construction unit: Shandong Heze Maosheng Wood Industry Co., Ltd.
Contact: Zhang Guoliang
Contact number: 13853079967
3. Name and contact information of the organization responsible for environmental impact assessment
Evaluation Agency: Jinan Borida Environmental Protection Technology Co., Ltd.
Contact: Zhang Gong
Contact number: 15589901680
Fourth, the environmental impact assessment work procedures and main work content
Working procedure: After receiving the power of attorney for the EIA, the evaluation unit will analyze the project status and conduct monitoring of the project in the project area to find out the pollutant discharge link, determine the amount of pollutants generated and the amount of pollutants discharged , and take pollution prevention according to the project. Measures technology, predicting the extent and impact of the project on the surrounding environment, and demonstrating the feasibility of project construction from the perspective of environmental protection; and based on the public opinions and suggestions reflected by public participation, propose that the construction unit should improve pollution prevention and improve the environment. Quality measures and countermeasures provide a scientific basis for decision-making departments.
Main work contents: engineering analysis, environmental quality status investigation, pollution prevention measures, environmental impact analysis and evaluation, environmental risk assessment, clean production analysis, economic profit and loss analysis , site selection rationality analysis, total amount control analysis, environmental management and monitoring plan And environmental impact assessment conclusions.
V. Main issues for public comment
1 Understanding of the proposed project and our company;
2 Recognition of the status quo of environmental quality;
3 recognition of the project site selection;
4 to understand the environmental problems that may be caused after the project is put into production;
5 measures taken in response to possible environmental pollution;
6 Comments and suggestions on the environmental protection work of this project.
6. The main way for the public to make comments
(1) Within 10 working days from the date of publication of the announcement, the construction unit or the entrusted environmental impact report preparation unit shall provide the public with relevant information inquiry and inspection services.
(2) If the public has environmental protection opinions on the proposed project, within 10 working days from the date of publication of this announcement, the construction unit or the environmental impact report preparation unit may express opinions by telephone or letter. Send your own comments in written form to the local environmental protection authority.
Announcement release unit: Shandong Heze Maosheng Wood Industry Co., Ltd.
Release date: November 3, 2016